Action on Resolution 23-026, a Resolution Authorizing Change Order No. 1, for Multi-Stack Fire Training Facility for the Brookings Fire Department; Fire Training Structures, LLC.
Body
Summary:
The Multi-Stack Fire Training Facility for the Brookings Fire Department is nearing completion. This change order increases the contract amount by $21,036.27, for a total of $516,007.27 based on an agreement between the City and the vendor, Fire Training Structures, LLC, to split the cost of South Dakota State Use Tax on public improvements, which was not included in the original bid.
Recommendation
Recommendation:
Staff recommends approval.