Title
Action on Resolution 22-080, a Resolution Authorizing Change Order No. 1 for 2022-08STI Street Maintenance & Overlay Project; Bowes Construction, Inc.
Body
Summary:
The 2022-08STI Street Maintenance & Overlay Project is currently in process. Additional work has been requested to be completed by the contractor, including repairing storm-damaged sidewalk, paving a gravel alley, and adding a curb to a new sidewalk ramp to better tie into the existing yard. Some of these quantities will be measured and paid as normal under the original contract, while other bid items were provided with new pricing.
Fiscal Impact:
The contract will be increased by $79,410.55 to include these additions to the project. The additional costs will be paid for under the Street & Sidewalk Improvement budget.
Recommendation
Recommendation:
Staff recommends approval.