Title
Action on Resolution 21-038, a Resolution Rejecting Bids on 2021-05STI, Concrete Maintenance Project.
Body
Summary:
This resolution will reject the bids for the 2021-05SWR Concrete Maintenance Project. The low bid of $655,589.78 from Timmons Construction was 40% higher than the Engineer’s Estimate of $468,505.50. The project is anticipated to be rebid at a later date.
Recommendation
Recommendation:
Staff recommends approving the resolution to reject the bids for the 2021-05STI Concrete Maintenance Project.