Title: Discussion on the Brookings Regional Landfill 3W Cell Construction.
Attachments: 1. Memo, 2. Presentation

Title

Discussion on the Brookings Regional Landfill 3W Cell Construction.

 

Body

Summary:

Luke Rodig, Project Manager for Burns and McDonnell, will present information regarding the Landfill 3W Cell construction Project.

 

Background:

The Brookings Regional Landfill does a cell construction project every 10 years. The last cell was constructed in 2010. The landfill puts money in a reserve fund each year to fund the project. 

 

Fiscal Impact:

The landfill has $2,100,000 set aside for the construction project. The estimated engineer cost is $1,800,000.