File #: RES 17-092    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/2/2017 In control: City Council
On agenda: 10/10/2017 Final action: 10/10/2017
Title: Action to approve Resolution 17-092, a Resolution authorizing Change Order No. 1 (Final) for 2017-10SSI, 2nd Street South Drainage Improvement Project; Clark Drew Construction, Inc.
Attachments: 1. Resolution, 2. Map

Title

Action to approve Resolution 17-092, a Resolution authorizing Change Order No. 1 (Final) for 2017-10SSI, 2nd Street South Drainage Improvement Project; Clark Drew Construction, Inc.

 

Body

Summary:

This resolution will approve Change Order No. 1 (Final) for 2017-10SSI, 2nd Street South Drainage Improvement Project, for a decrease of $84.20 to close out the contract.

 

Background:

The 2nd Street South Drainage Improvement Project is located on the north side of 2nd Street South between Airport Avenue and Division Avenue, as shown on the attached map.  The project was a neighborhood drainage improvement project and it included constructing an 8-foot wide concrete valley gutter with 18-inch high side walls, erosion control blanket and seeding.

 

The contractor has completed the work and the project is ready to be closed out.  This change order will adjust plan quantities to as-constructed quantities for a total decrease of $84.20 to close out the project.  The project summary is as follows:

 

Original Contract Price:                                                                                                                                                   $143,225.89

Increase from Previous Change Orders:                                                                                                          $0.00

Contract Price Prior to this Change Order:                                                                                    $143,225.89

Decrease Increase of this Change Order (No. 1):                                                               $84.20

Contract Price incorporating this Change Order:                                                               $143,141.69

 

Fiscal Impact:

There will be a reduction of $84.20 to the contract with Clark Drew Construction, Inc. 

 

Recommendation

Recommendation:

Staff recommends approval.

 

Body2

Attachments:

Resolution

Map