Action on Resolution 21-106, a Resolution Authorizing Change Order No. 1 (Final) for 2021-08STI, Overlay Project; Bowes Construction, Inc.
Body
Summary:
This resolution will approve Change Order Number 1 (Final) for an increase of $65,181.29 to the contract amount to close out the project. The increased cost was due to additional work being added to the project including storm sewer improvements in the Faculty Drive area as well as a sidewalk connection to the Nature Park at the end of Avalon Circle. To accommodate the additional work, the substantial and final completion dates shall be extended by 10 working days. The additional work on the project is within the budgeted amount.
Recommendation
Recommendation:
Staff recommends approval.