Action on Resolution 18-091, a Resolution Authorizing Change Order No. 1 (Final) for 2018-01 Gateway Landscaping Improvement Project, Kerry’s Landscaping & Irrigation.
Body
Summary:
This resolution will approve Change Order No. 1 (Final) for 2018-01 Gateway Landscaping Improvement Project with Kerry’s Landscaping & Irrigation for a total increase of $3,109.10 to the contract to close out the project.
Background:
The Gateway Landscaping Improvement Project is located in the medians along 6th Street between 22nd Avenue and 34th Avenue. The landscaping improvements were designed by Confluence and included irrigation, tree plantings, turf seeding, and other vegetative plantings.
The project has been completed and is ready to be closed out. This change order will increase the contract price by $3,109.10 associated with extending copper irrigation water services to the center of the median in four locations, repair copper riser pipe kinked below grade in two locations, and installing a shut off valve, blow out connection and valve box at the existing water service blow out riser pipe at four locations. The summary is as follows:
Original Contract Price: $87,260.94
Increase from Previously Approved Change Orders: $0.00
Contract Price Prior to this Change Order: $87,260.94
Increase of this Change Order (No. 1 Final): $3,109.10
Contract Price incorporating this Change Order: $90,370.04
Fiscal Impact:
There will be an increase of $3,109.10 to the contract to close out the project.
Recommendation
Recommendation:
Staff recommends approval of the change order.