Action on Resolution 24-088, a Resolution authorizing Change Order No. 1 for 2024-09STI Concrete Maintenance Project; Timmons Construction, Inc.
Body
Summary:
The 2024-09STI Concrete Maintenance Project is complete. The proposed resolution is the final balancing change order for the project and will increase the contract awarded to Timmons Construction, Inc., Brookings, SD in the amount of $22,914.50 (7%). The increased amount is for additional curb and gutter repairs, and additional sidewalk replaced for homeowners as part of the residential trip hazard program. Staff recommends approval of this resolution to close out this contract/project with Timmons Construction, Inc.