File #: RES 23-055    Version: 1 Name: Resolution - Change Order 1 for 2023-04STI 22nd Ave.
Type: Resolution Status: Passed
File created: 6/12/2023 In control: City Council
On agenda: 6/13/2023 Final action: 6/13/2023
Title: Action on Resolution 23-055: Change Order No. 1 for 2023-04STI 22nd Avenue Phase 2 Reconstruction Project; Timmons Construction Company.
Attachments: 1. Memo, 2. Resolution

Title

Action on Resolution 23-055: Change Order No. 1 for 2023-04STI 22nd Avenue Phase 2 Reconstruction Project; Timmons Construction Company.

 

Body

Summary:

The proposed resolution will increase the contract amount of the 2023-04STI 22nd Avenue Phase 2 Reconstruction Project, awarded to Timmons Construction Co., Brookings, SD, in the amount of $142,154.29 (3.5%).  The increased amount is for 1) additional work required by South Dakota State Department of Agriculture and Natural Resources (DANR), 2) acceleration of the project; target the opening of the Orchard / 22nd Avenue and 8th Street South / 22nd Avenue intersections, prior to the start of school on August 23, 2023, and 3) improvements to the traffic control plan/signage.

 

Financial Impact:

If approved, the contract with Timmons Construction Co. will be increased in the amount of $142,154.29.

 

Recommendation

Recommendation:

Staff recommends approval as presented.  If not approved, the construction project will be delayed.

 