Skip to main content
File #: RES 23-076    Version: 1 Name: Resolution - Change Order 1 for 2023-04STI 22nd Ave.
Type: Resolution Status: Passed
File created: 8/29/2023 In control: City Council
On agenda: 9/12/2023 Final action: 9/12/2023
Title: Action on Resolution 23-076, a Resolution authorizing Change Order No. 1 for 2023-08STI Street Maintenance and Overlay Project; Bowes Construction Inc.
Attachments: 1. Memo

Title

Action on Resolution 23-076, a Resolution authorizing Change Order No. 1 for 2023-08STI Street Maintenance and Overlay Project; Bowes Construction Inc.

 

Body

Summary:

The proposed resolution will increase the contract amount of the 2023-08STI Street Maintenance and Overlay Project; awarded to Bowes Construction Inc. Brookings, SD, in the amount of $15,500 (0.6%).  The increased amount is for 1) additional work on Harvey Dunn for solid waste collection and a temporary parking pad, 2) addition of a reinforced concrete sidewalk bridge on Park Avenue as part of the valley gutter at this location.

 

Financial Impact:

If approved, the contract with Bowes Construction Inc. will be increased in the amount of $15,500.

 

Recommendation

Recommendation:

Staff recommends approval.

 

Body2

Attachments:

Memo

Resolution