Title
Action on Resolution 24-109, a Resolution authorizing Change Order No. 1 for Project 2024-08STI Street Maintenance and Overlay Project: Bowes Construction.
Body
Summary and Recommended Action:
Staff recommends approval of the proposed resolution which is the final balancing change order for the 2024-08STI Street Maintenance and Overlay Project. The resolution will increase the contract awarded to Bowes Construction, Brookings, SD, in the amount of $127,664.57 (10%). The increased amount stems from the unforeseen subsurface conditions in 7th Street, as well as the addition of 14th Avenue between 3rd and 4th Street due to pavement failure that was deemed imminent. The change order includes six (6) days of liquidated damages at $475 per day ($2,850) for the days past the final completion date of October 20, 2024. The adjusted contract remains below the original estimate and budgeted appropriations by $113,719.58.