Title
Action on Resolution 21-116, a Resolution Authorizing Change Order No. 1 (Final) for Project 2021-04STI Swiftel Pavement Reconstruction Project; Timmons Construction, Inc.
Body
Summary:
The 2021 Swiftel Paving Project is completed and ready to be closed out. The final cost of the project is $130,894.50, which is an increase of $21,362.00 for the original contract price of $109,532.50. The increased cost was due to replacing more sidewalk along the Larson Ice Arena to address several trip hazards and additional gravel base course to address the inadequate base section under the pavement section.
This Resolution will approve Change Order No. 1 (Final) for an increase of $21,362.00 to the contract amount to close out the project. The additional amount is within the project budget.
Recommendation
Recommendation:
Staff recommends approval.