This resolution will approve Change Order No. 1 to the Apron and Taxilane Improvement Project for a decrease of $17,794.17.
The Change Order adjusts the as-built quantities of various bid items. In addition, this Change Order also adds 1 Underdrain Headwall.
The project summary is as follows:
Original Contract Price: $2,255,787.40
Change from Previously Approved Change Order: $0.00
Contract Price Prior to this Change Order: $2,255,787.40
Increase of this Change Order: $3,800.00
Decrease of this Change Order: ($21,594.17)
New Contract Prior After this Change Order: $2,237,993.23
This resolution will approve Change Order No. 1 for a net decrease of $17,794.17 to the contract amount.